PMP考試練習(xí)題一: During project implementation, a key team member in a balanced matrix organization is transferred to another project. The project is now in jeopardy of being delayed. To prevent this situation, what should the project manager have done? A. Defined the team member’s project availability and obtained agreement in the staff release plan B. Outsourced the task because the team member had too many projects C. Prepared the team members to work overtime so they could work on both projects D.Created a buffer in the project schedule to prepare for such occurrences 在項(xiàng)目實(shí)施期間,在一個(gè)平衡矩陣式組織中一名關(guān)鍵團(tuán)隊(duì)成員被調(diào)任至另一個(gè)項(xiàng)目上。項(xiàng)目目前面臨著延期的危險(xiǎn)。為避免這種情況,項(xiàng)目經(jīng)理應(yīng)該事先做什么? A.確定團(tuán)隊(duì)成員的項(xiàng)目可用性,并在人員遣散計(jì)劃中獲得同意 B.外包任務(wù),因?yàn)樵搱F(tuán)隊(duì)成員負(fù)責(zé)的項(xiàng)目過(guò)多 C.讓該團(tuán)隊(duì)成員準(zhǔn)備加班工作,讓他可以同時(shí)為兩個(gè)項(xiàng)目工作 D.在項(xiàng)目進(jìn)度計(jì)劃中創(chuàng)建一個(gè)緩沖時(shí)間,為這種情況的發(fā)生做準(zhǔn)備 PMP考試答案解析:儲(chǔ)備分析,安排時(shí)間緩沖。 PMP考試參考答案:D PMP考試練習(xí)題二 During a project kick-off meeting, the project sponsor asks for several changes related to the scope, schedule, and human resources assigned to the project. The project team realizes that the planning work was improperly completed. What best practice should the project manager have implemented to prevent this? A. Updated the documentation to project baselines. B. Scheduled periodic planning meetings with all key project stakeholders C. Sent minutes of the project meetings to the project sponsor D. Registered the project sponsor's requests in the issue log 在項(xiàng)目啟動(dòng)大會(huì)上,項(xiàng)目發(fā)起人要求對(duì)范圍,進(jìn)度和分配給項(xiàng)目的人力資源進(jìn)行多項(xiàng)變更。項(xiàng)目團(tuán)隊(duì)發(fā)現(xiàn)規(guī)劃工作沒(méi)有正確完成。若要防止這個(gè)問(wèn)題,項(xiàng)目經(jīng)理應(yīng)該事先實(shí)施並最佳實(shí)踐是什么? A.將文檔更新至項(xiàng)目基準(zhǔn) B.定期安排與所有關(guān)鍵項(xiàng)目干系人召開(kāi)規(guī)劃會(huì)議 C.向項(xiàng)目發(fā)起人發(fā)送項(xiàng)目會(huì)議紀(jì)要 D.將項(xiàng)目發(fā)起人的請(qǐng)求登記在問(wèn)題日志中 PMP考試答案解析:定期與關(guān)鍵干系人開(kāi)會(huì),讓他們積極參與項(xiàng)目,表達(dá)自己的需求與想法。 PMP考試參考答案:B |